Re: Procurement Confirmation Wizard only one level?

$
0
0

Hi Peter,

 

In Procurement Wizard you can't do PO and Production Orders. 

 

In MRP Wizard, you can create.

 

MRP calculates gross requirements for the highest

bill of materials (BoM) level, based on existing inventory, sales orders,

purchase orders, production orders, forecasts, and so on. It calculates gross

requirements at the lowest BOM levels by carrying down net parent demands

through the BOM structure. Dependent levels might have their own requirements,

based on sales orders and forecasts.


Thanks,