Hi All,
I have some requirement like,I have two input schedule one is Plan 1 and another one is Plan 2.Plan 1 basically use for input data, but user cant change anything in Plan 1 input due to some other reason, if any modification or changes are require then they change it from plan 2 input schedule.So select and change context for two input schedule it's lengthy and risk of wrong context selection.
Now I want to give the facility to the user when they work in plan 1 input schedule the context for plan 2 input schedule automatically set.There is no need to select or change member from plan 2 input.The context once set for Plan 1 input which is also automatically set for plan 2 input.
Best Regards
Mayur