Hi Bibhuti,
Check whether you have assigned procurement type "F" in MRP-2 view for Raw material creation(MM01).Also give planning strategy as 10 in MRP-3 view for raw material.
Select "PR+reservation for WBS" as procurement indicator in Network profile.
Do the above changes, Run the MD51 MRP Run.
Best regards,
Sriramm