Hello PP Colleagues !
I need your guide please.
My client want that in MD04 the PIRs don't create planned order , but a planned order can be created for the Dynamic safety stock .
I'm trying with the customizing item: Production>Material Requirement Planning>Master Date>Independent Requirement Parameters> Define Consumption Mode and Period of Adjustment
When I run MRP , the system doesn't create planned order for PIR's, it is ok for my scenary, but the planned order expected to replenished up to the target stock level (11 days) , neither is created.
Can you tell me please, if is posible to create planned order to replenished up the target stock without create planned orders for PIRs ?
Thanks a lot for your comment.
Vero