Plan value in RA (KKA2) different from CJ20N

$
0
0

Dears, A project plan and budget got revised several times due to many changes from customer, now we got the final estimations and updated the same in CJ20N, however when we are running RA for the same project for June 2015, its showing different cost as comparing to CJ20N. Could you please help us to make correction in RA to be in sync with CJ20N.. Thanks, Lokesh