Re: Scheduling time not determined in process order

$
0
0

Hello

 

 

I have created the following documents with the basic master data for the proper scheduling scheduling of a production order:

 

CRP Basic Settings Part 1 - Work Center

CRP Basic Settings Part 2 – Routing

CRP Basic Settings Part 3 – Production Order

 

The information from these documents can be also applied for process orders, with some slight differences:

 

- On the resource, you must use "other formula" instead of setup and processing.

- On the master recipe, you must define relationships for the operations.

 

See also the following note, which explains the scheduling of a process order in detail:

 

151503  - Consulting: Scheduling of process order

 

Regards

Caetano