Thank you both. It might take me a bit to figure out SPRO. I must not have full rights since I seem to be in display mode. I also searched for the setting, and have not found it.
I apologize if my scenario was confusing.
The order was created on 10/29/2014 last year, but we did not make the material until 1/24 this year.
In meantime, a revision to the material went through. The material rev = 11/21/2014. The recipe still says 10/29/2014.
My logic tells me this is the disconnect. That because the material changed, both the order and the recipe would all need to say 11/21/2014. My peers do not think so.
I am eager to try adding the inspection type 89, but haven't gotten there yet.