Hi Varshal,
My GR is valuated & actual cost is booked (see in screen shot) my concern is why material purchase cost is seen under Planned cost column in report S_ALR_87013532 / 33 - Plan/Actual/Variance , basically I want see Planned Vs Actual cost for Project for cost planned by CJ40 . But my actual purchase cost is seen under planned column & also its ADD UP in Plan cost so my as per screen shot my Actual Plan cost by CJ40 for Project is Rs 140000 but now its seen Rs 140465 by adding Rs 465 as material cost .
Thanks,
Virendra