Hi Experts,
I am testing MATP with RBA, I could not see the planned orders in ATP tree structure once I saved the sales order in ECC.
Scenario -
I have product A (header) and A1 & A2 are the components of product A (Header)
I have stock on component A1 - 100 & component A2 - 100, STOCK on header material A -0
I have created sales order for header material A - customer requested quantity 201.
THEN system is confirming the sales order only for 100 qty because the components A1 & A2 stock available only 100.
I can see the dependent demand in rrp3 for Components A1 and A2
I can see the planned order in rrp3 for header material A
BUT I could not see any planned orders either in /SAPAPO/RRP_ATP2PPDS - Conversion ATP Tree Structures -> Production Planning OR
/SAPAPO/ATREE_DSP - ATP Tree Structures
below is the error message I am getting in the transaction -/SAPAPO/RRP_ATP2PPDS - Conversion ATP Tree Structure
What could be the wrong in the above case.. can you please suggest.. Advance thanks for your information.